About Aquamaison
Location & Contact
   
  Services
Consulting
New Construction
Retrofit
Concrete Barges
   
FAQ
Construction
Process
Concrete Barges
Costs
   
Links
Marin County
Building Code
Floating Homes Association
Web Cam
Tides
Weather
   
   
   
   


Concrete Barges

Concrete barges float because of the sheer volume of water displaced by the barge. Acting in accordance with the laws of physics, the weight of water displaced equals the weight of the barge.

The barges are formed atop two steel cradles with a total of 12 wheels that run on railroad tracks which extend into the bay. A plywood deck is formed between the steel cradles, and wall forms are erected on the deck.

The next phase is the installation of reinforcing steel. In a 16 x 36 barge, there is approximately 4000 lbs. of reinforcing, comprising #4 bars at 12” centers both ways in the walls and floor slab; #5 bars at 6” centers in top of the floor slab and #6 bars at the top and bottom of the walls.

 
  Boat shaped barge for the SS Maggie South 40 Pier, Waldo Point Harbor, Sausalito, CA.

When reinforcing placement is complete and it has been inspected by the structural engineer, inside wall forms are installed, lined, plumbed and braced.

 
  Home under construction for 27 Liberty Dock, Waldo Point Harbor, Sausalito, CA; New barge recently poured, ready for wall form removal and epoxy coating.
Concrete is usually poured beginning at 7:00 a.m. to take advantage of cooler weather. The pour takes from 2 to 4 hours, depending on the barge size. Design strength for the concrete is 4000 psi at 28 days, but this strength is usually attained at 7 days. The mix contains 7 sacks of cement per cubic yard of concrete and some plastecising admixtures and is delivered to the site with a maximum slump of 3” which is quite dry, but is workable because of the admixtures. A very important element of high concrete strength and minimum shrinkage is low water-to-cement ratio.

Wall forms can be removed several days after pouring. Then the “snap tie” (ties that hold the forms together) holes are plugged with a pre-cast cement cone and urethane caulking, then the walls receive two coats of cold tar epoxy coating.

The barge can be launched when the concrete reaches design strength which is normally about 7 days, but launching is usually 10-14 days after pouring.

As of December 1st 2013 the price for a new barge is $81 per square foot for a barge 16' x 32' x 6', making the price $41,472. All barges have fusion epoxy coated reinforcing, and the exterior walls have two coats of polyurethane epoxy paint.Prices for barges larger than 16' x 32' x 6' will be quoted after specific design is produced by a licensed structural engineer.

Some concrete barges built by the military during WWII are being used as houseboat hulls, and with better concrete and two coats of cold tar epoxy, today’s barges can be expected to last at least 40 years. With the use of fusion coated reinforcing the life expectancy exceeds 80 years.

Aquamaison, Inc. began building concrete barges in 1978, and from that time on was having reinforcing steel designed and inspected by an engineer, taking concrete samples for testing, and casting into each barge a date, barge number, and the name “Aquamaison Inc.”

It was not until four years later that the County included these procedures in the Houseboat Code, for other builders to follow.

Each barge pour has continuous on-site monitoring to ensure a monolithic structure, a vital element for waterproofness and a quality product, for which Aquamaison Inc. is renowned.